How do I set priorities to enable tasks to be carried out in a set order.

RE: MS Project

Hi Frank

Thank you for your question.

Could you please clarify your question with a specific example. While Project does not naturally lend itself to creating a series of prioritised tasks, there are a number of possible routes forward depending on the nature of the tasks

Regards

Stephen

MS Project tip:

Create own ribbon tab - Project 2010

a. In Project click on the File tab
b. Select Options from left hand side
c. Choose the Customize Ribbon section
d. Click the New Tab button (below the list of tabs on the right hand side of the dialog box)
e. Select the New Tab (Custom) and enter a name, by clicking the Rename button (below the list of tabs on the right hand side of the dialog box)
f. Select the New Group (Custom) and enter a name, by clicking the Rename button (below the list of tabs on the right hand side of the dialog box)
g. Add commands to your tab and group by locating them on the list on the right hand side (remembering that you can change the list using the drop down box at the top of the list of commands) and clicking the Add button between the two panes to add them to your tab and group
h. You can rearrange the commands in your group, the groups on any tab or the tabs, using the up and down arrow buttons beside the list of tabs.
i. Click OK to apply your changes