How do I set task constraints?
RE: Task constraints
Hi Andrea
Thankyou for your question
To set task constraints first select the task you want to modify, in the GANTT chart view, and open the task information dialog by double clicking on the task.
If you the select the advanced tab, you can choose a task constraint and a date for it in the relevant combo boxes.
Regards
Stephen