How do I assign work to be covered over the weekend
RE: Weekend
Hi, on the relevant calendar, (Tools/change working time), make sure Sat/Sun are set for non-default working time
Forum home » Delegate support and help forum » Microsoft Project Training and help » ms project manager courses london - Weekend
Ava has attended:
Project Intro Intermediate course
How do I assign work to be covered over the weekend
Hi, on the relevant calendar, (Tools/change working time), make sure Sat/Sun are set for non-default working time
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question.
Our Microsoft Qualified trainers will then respond within 24 hours (working days).
Frequently Asked Questions
What does 'Resolved' mean?
Any suggestions, questions or comments? Please post in the Improve the forum thread.
a. In Project, click on the File tab
b. Select Options from left hand side
c. Click on Schedule to set the scheduling options
d. Set the Default Task type box to your chosen option
i. Generally if you plan/estimate your projects using durations you should use fixed duration, and untick the box New tasks are effort driven, if you plan/estimate with person hours use fixed work, or for plans estimated with the proportion of resources time use fixed units, and untick the box New tasks are effort driven)
e. Click OK to apply your changes