Forum home » Delegate support and help forum » Microsoft Project Training and help » microsoft project training seminar - Tracking Progress

microsoft project training seminar - Tracking Progress

ResolvedVersion Standard

Stuart has attended:
Project Introduction course

Tracking Progress

How do you track resources against the baseline

RE: Tracking Progress

Hi Stuart

First save your baseline (Tools>Tracking>Set Baseline)

Now when you mark progress any changes will be displayed in the Tracking Gantt view. The grey bars represent your baseline position with the coloured bars showing your live project.

Hope this is helpful,

Kind regards,

Andrew

MS Project tip:

Entering Days

To type in a day of the week, or its three letter abbreviation, in a Date field type "Monday" or "Mon", and Project will show the date for the next Monday after the current date.

View all MS Project hints and tips