Is there a limit of how many calendars you can set up?

RE: MS Project, Calendar, Working Time

For all practical purposes the number of calendars is unlimited.
You will often have a calendar for each individual resource together with a number of base calandars, e.g "Standard", "24 hour" etc.
The real limit will be determined by what is convienient to work with


 

MS Project tip:

Autofit column width – Project (all versions)

At the top of the columns where each column name is located (Task Name, Duration, etc.), hover over the vertical column line which you want to move.

A short bold vertical line will appear, with horizontal arrows pointing left and right.

Left click and hold this icon and it will permit you to grab the column line, allowing you to move it left or right to your desired location.