Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

class microsoft project training - milestone

Forum home » Delegate support and help forum » Microsoft Project Training and help » class microsoft project training - Milestone

class microsoft project training - Milestone

ResolvedVersion Standard

Laura has attended:
Project Intro Intermediate course

Milestone

how do I create a milestone

RE: Milestone

Hi Laura

Set your task's duration to zero days to create a milestone

Let us know if you have any further questions.

Kind regards,

Andrew

MS Project tip:

Format individual bars on your GANTT chart

To draw attention to a bar on your Gantt chart simply double click it. From the dialogue box that opens make your selection of text and bar modifications.

View all MS Project hints and tips