management microsoft project training - Multiple project linking

ResolvedVersion Standard

Micheal has attended:
Project Intro Intermediate course

Multiple project linking

During linking of 2 projects, is it possible to link task from 1 project to any part of the other or is it just the last task of the 1st project linking to the first task of the second?

Thanks

RE: Multiple project linking

it is possible, depending if there are any constraints or not.

MS Project tip:

Compare Work and Duration

Duration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field.