microsoft+project+courses - Non-work time

ResolvedVersion Standard

Simon has attended:
Project Intro Intermediate course

Non-work time

How do I add non work time to my gantt chart eg bank holiday

RE: non-work time

Hi, on the relevant calendar, (Tools/change working time), make sure Sat/Sun are set for non-default working time.

Hope that helps

Tracy

MS Project tip:

Project Community

in the help menu type "Tips" then select "Ask the Project community" this takes you into microsofts site where you can ask questions to lots of knowledgeable people.They make up an online group of experienced Project users who answer questions and provide solutions and tips.