How do I put a lag of 3 hours between two tasks?
RE: MS Project
Hi Henrietta,
You add lag (and lead) time to the link that joins your tasks.
Double click on a link and from the dependency dialogue box that appears add the amount of lag you require.
If you make links between tasks by double clicking the task and choosing the predecessor tab you will see that when you choose your predecessor you can also specify lag or lead time.
I hope this helps - do let us know if you have any further questions
Kind regards,
Tracy