RE: Resource
Hi Pedro. As usual with MS Office products there are a number of ways to achieve this. The two simplest ways are to double click on the task, select the resource tab and add resources in the list at the bottom. Secondly, in the entry table in Gantt Chart view, insert the Resources column and simply assign them to the task through the dropdown box.
Hope this helps,
Anthony