RE: milestone
Hi Aurore. A milestone is simply defined by setting the duration in the entry table of that task to 0 days. It is a one-off event that has to be met for the project to succeed!
Forum home » Delegate support and help forum » Microsoft Project Training and help » microsoft project training courses - Milestone
Hi Aurore. A milestone is simply defined by setting the duration in the entry table of that task to 0 days. It is a one-off event that has to be met for the project to succeed!
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question.
Our Microsoft Qualified trainers will then respond within 24 hours (working days).
Frequently Asked Questions
What does 'Resolved' mean?
Any suggestions, questions or comments? Please post in the Improve the forum thread.
a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.