microsoft project training - Split tasks

ResolvedVersion Standard

Martyn has attended:
Project Intermediate course

Split tasks

how do you split tasks.

RE: split tasks

Hi Martyn

Thank you for your question.

To split a task:

1. In the Gantt chart, right-click on the box representing the task you wish to split.
2. Select Split task from the menu.
3. Hold your mouse over the box representing the task, at the point you wish to split it. Then drag to create the split.

Amanda

MS Project tip:

Avoid Accidental Constraints

The initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.)