Forum home » Delegate support and help forum » Microsoft Project Training and help » microsoft project training course london - Indentation

microsoft project training course london - Indentation

ResolvedVersion Standard

Larry has attended:
Project Intermediate course

Indentation

How many indentation levels are available

RE: Indentation

Hi Larry

Thanks for your question.

There are 9 levels of indentation available in Project (see the Show button near the left-hand side of the Formatting toolbar).

Amanda

MS Project tip:

Keep constraining dates to a minimum

As far as possible avoid fixing the dates of your tasks. For example try to steer of clear dragging task bars in the Gantt chart to move them on the timeline or entering dates directly into the Start / Finish fields.

Date constraints such as these limit Microsoft Project's ability to automatically adjust your project whenever you add, remove or modify the duration of your tasks. Instead use the logic in your task dependencies that link your tasks to enable Project to calculate the start and finish dates for you.

View all MS Project hints and tips