microsoft project training seminar - resources

Forum home » Delegate support and help forum » Microsoft Project Training and help » microsoft project training seminar - Resources

microsoft project training seminar - Resources

resolvedResolved · Low Priority · Version Standard

Ben has attended:
Project Intro Intermediate course
Project Intro Intermediate course

Resources

how do you attach a resource to a task?

RE: resources

Hi Ben

Thanks for your question.

You can assign a resource to a task by:

1 On the View menu, click Gantt Chart.
2 In the Task Name field, select the task that you want to assign a resource to.
3 Click Assign Resources .

You can also use the Resources side pane to quickly assign people and equipment to tasks.

1. On the Project Guide toolbar, click Resources and then click Assign people and equipment to tasks.
2. Then follow the instructions that appear in the side pane.

I hope this helps.
Amanda


 

MS Project tip:

Create own ribbon tab - Project 2010

a. In Project click on the File tab
b. Select Options from left hand side
c. Choose the Customize Ribbon section
d. Click the New Tab button (below the list of tabs on the right hand side of the dialog box)
e. Select the New Tab (Custom) and enter a name, by clicking the Rename button (below the list of tabs on the right hand side of the dialog box)
f. Select the New Group (Custom) and enter a name, by clicking the Rename button (below the list of tabs on the right hand side of the dialog box)
g. Add commands to your tab and group by locating them on the list on the right hand side (remembering that you can change the list using the drop down box at the top of the list of commands) and clicking the Add button between the two panes to add them to your tab and group
h. You can rearrange the commands in your group, the groups on any tab or the tabs, using the up and down arrow buttons beside the list of tabs.
i. Click OK to apply your changes

View all MS Project hints and tips