ms project training in london - standardise calendars and workin

Forum home » Delegate support and help forum » Microsoft Project Training and help » ms project training in london - Standardise calendars and working time

ms project training in london - Standardise calendars and working time

resolvedResolved · Low Priority · Version Standard

Ibrahim has attended:
Excel Advanced course
Excel VBA Intro Intermediate course

Standardise calendars and working time

Is there a quick way to standardise calendars and working times across multiple project plans without changing their schedule?

For example, when several Project documents covering a several-month period need to be integrated into one plan and their original authors have used templates with slightly different assumptions?

RE: Standardise calendars and working time

Ibrahim

Are you using project server?

regards

dave

RE: Standardise calendars and working time

Hi Dave,

No, we aren't using Project Server.

Regards,

Ibrahim

RE: Standardise calendars and working time

Ibrahim,

sorry for very late reply, but i cant find an answer to this, have you?

david

RE: Standardise calendars and working time

No, I'm afraid not

RE: Standardise calendars and working time

neither have I


 

MS Project tip:

Avoid Accidental Constraints

The initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.)

View all MS Project hints and tips


Server loaded in 0.07 secs.