Ibrahim has attended:
Excel Advanced course
Excel VBA Intro Intermediate course
Standardise calendars and working time
Is there a quick way to standardise calendars and working times across multiple project plans without changing their schedule?
For example, when several Project documents covering a several-month period need to be integrated into one plan and their original authors have used templates with slightly different assumptions?
RE: Standardise calendars and working time
Ibrahim
Are you using project server?
regards
dave
RE: Standardise calendars and working time
Hi Dave,
No, we aren't using Project Server.
Regards,
Ibrahim
RE: Standardise calendars and working time
Ibrahim,
sorry for very late reply, but i cant find an answer to this, have you?
david
RE: Standardise calendars and working time
No, I'm afraid not
RE: Standardise calendars and working time
neither have I