A project one of my colleagues is working on shows a % completion figure of 11%. However, given he is ahead on all current/recent tasks this figure seems incorrect. The project started on 6 April 2017, runs to late January 2019 and is almost 5 months in and on track. By my calculation 5 months of completed work into a 22 month project should show around 20% complete. All the recent and current tasks have been marked as 100% complete.
What might be causing this issue?
I'll be happy to email the plan if required.
RE: Project completion calculation
Hi Jenny
I might need to see the file to see what the problem could be.
Please could you email it to info@microsoft-training.co.uk
thank you
Wendy
RE: Project completion calculation
Hi Jenny
I have received your file, thank you.
Just some questions regarding this.
Has your colleague just marked the task off as 100% complete or has he used the update task function?
If a task has been completed ahead of schedule, you need to use Task > Mark on Track > Update tasks to add an earlier completion date.
I can't see any calculation problems in the file itself so I think the completion tasks may have been completed incorrectly.
Thank you
Kind regards
Wendy
Will be marked as resolved in 5 days
Notice: This is an automated message. Due to inactivity, this forum post will be marked as 'resolved' if there are no further responses in the next 5 days.
Will be marked as resolved in 5 days
Notice: This is an automated message. Due to inactivity, this forum post will be marked as 'resolved' if there are no further responses in the next 5 days.