Forum home » Delegate support and help forum » Microsoft Project Training and help » microsoft project course - Milestones

microsoft project course - Milestones

ResolvedVersion Standard

trainer has attended:
Excel Introduction course
Excel Intermediate course

Milestones

how do i create a link

RE: milestones

Hi There are at least five ways of doing this. Three of the most common ways however are:

left click (and drag) from one bar in the Gantt chart to another
block select two or more tasks and click on the link tasks button on the toolbar
double click a task and from the predecessors tab choose a task

Hope this helps - do let us know if you have any further questions.
Thanks

Andrew

MS Project tip:

Compare Work and Duration

Duration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field.