Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

calculation periods and duration

Forum home » Delegate support and help forum » Microsoft Project Training and help » Calculation Periods and Duration from start and end dates

Calculation Periods and Duration from start and end dates

ResolvedVersion 2010

julia has attended:
Project Advanced course

Calculation Periods and Duration from start and end dates

As the timeline in Project 2013 is restrictive when dealing with lots of Gantt lines (I have 64 initiatives in this portfolio), I would like to use the Visual Reporting to provide information that I can plug into the Excel Project Gantt Planner template. In that Excel Project Gantt planner, I need to calculate start dates and time in MSP into periods – which I am happy to do (if I knew how to do it). So I need to customise a column, using a formula to calculate.

1.
Plan Start Period Number
Assumption P1 is the first week in 2016
Formula: Look at base line date and assign the start period, e.g. 4/1/16 is P1

2.
Plan duration number of periods
Formula: Look at the baseline start date and baseline end date and calculate how many periods, e.g. statt4/1/16, finish 15/1/16 number of periods = 2

I will 2 other calculations e.g. Actual Start and Actual Duration, but I will be able to work those out form the formulas above.

Many thanks.

RE: Calculation Periods and Duration from start and end dates

Hi Julia,

This is a very good question.

While we can do lookups (Drop downs) using custom Fields we can not use the Vlookup function from Excel.

I think I'm aware of the Excel Gantt Planner you are referring to.

Once I've Exported/Copied the Project Data into Excel, I would write a Vlookup to pull the Period number from a date table.

I've attached an Excel File with an example lookup so you
can "Convert" the data into Periods/Weeks

Kind regards

Richard Bailey
Microsoft Certified Trainer

Best STL - https://www.stl-training.co.uk
98%+ recommend us

London's leader with UK wide delivery in Microsoft Office training and management training to global brands, FTSE 100, SME's and the public sector

Attached files...

Period Lookup.xlsx

Wed 7 Sep 2016: Automatically marked as resolved.

MS Project tip:

Compare Work and Duration

Duration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.1 secs.