Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

shading holiday periods

Forum home » Delegate support and help forum » Microsoft Project Training and help » Shading holiday periods

Shading holiday periods

ResolvedVersion 2010

John has attended:
Project Introduction course

Shading holiday periods



I have forgotten how to shade and print holiday priods and non-working times

RE: shading holiday periods

Hi John

Non working time normally shows as grey columns. But it only if the timescale is set to count in days.
To do this quickly in Project select View tab, Days from the Timescale dropdown.

To change the colour right click on the Gantt Chart and choose Non Working Time, Color.

Regards
Doug
Best STL

Fri 9 Oct 2015: Automatically marked as resolved.

MS Project tip:

Compare Work and Duration

Duration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.1 secs.