Resource pool with sharepoint


How does the link on saving work with resource pool and share point

RE: Resource pool with sharepoint

Hi Suzan

It looks like MS Project 2013 won't allow you to maintain a resource pool when stored on Sharepoint. However I have found two possible work-arounds that you might find interesting. I also suspect a search for third-party plug-ins might also offer you options.

Here are the articles I found after a bit of hunting...

https://social.technet.microsoft.com/Forums/sqlserver/en-US/275b028f-3b7a-42f7-9cb1-126ec138847c/project-2013-projects-subprojects-resource-pool-and-sharepoint-sync-to-task-lists-not?forum=projectprofessional2010general

and

https://social.technet.microsoft.com/Forums/projectserver/en-US/c6d03c14-8b67-4f54-88fc-8428e860a401/resource-pool-with-sharepoint?forum=projectprofessional2010general

I hope you find these helpful. Do let me know if you have any other questions.

Kind regards,
Andrew

Tue 24 Mar 2015: Automatically marked as resolved.

MS Project tip:

Avoid Accidental Constraints

The initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.)

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.1 secs.