Anjani has attended:
Project Intermediate course
MS project timeline
Is whether there is a way to pull more information from a Gantt view into a timeline view? At present I have a title and date but there’s a host of other information I would like to include without having to type everything in notes on the timeline itself.
RE: MS project timeline
Hi Anjani
Yes you can add many things to the Timeline.
Start by clicking on the Timeline
Select the tab Format (Timescale Tools)
Then click Existing Tasks
You can now click on the tasks, milestones or summary tasks you want to show on the Timeline.
Also if you run out of space click on Display as Callout and also change the number of lines to display.
Hope that helps
Regards
Doug Dunn
Best STL