MS project 2010
how do i move a project?
RE: MS project 2010
Hello Colette,
Hope you enjoyed your Microsoft Project course with Best STL.
Thank you for your question regarding how to move a project.
I am presuming you wish to move the schedule? If so, go to the Project ribbon and in the Schedule group click the Move Project button. If you have any deadlines in your schedule you must indicate whether these should be moved or not. The default for this is to move deadlines. This is a very powerful option since it also moves all the constraints in the project.
I hope this resolves your question. If it has, please mark this question as resolved.
If you require further assistance, please reply to this post. Or perhaps you have another Microsoft Office question?
Have a great day.
Regards,
Rodney