Melanie has attended:
Project Intro Intermediate course
Progress Lines
What are the steps to view progress files?
RE: Progress Lines
Hi Melanie
Thanks for your question.
To add progress lines go to the Tools menu, choose Tracking then Add progress lines.
From the dialogue box that appears you can choose to always display current progress line at the current date (which creates a line that moves through your project, showing today's date) or you could choose to display your progress line at the status date of your project.
Alternatively if you turn on your tracking tool bar (Tools > Customise then make sure the Tracking toolbar has a tick beside it) you can click on the add progress line button. Then click at the point on your Gantt chart where you would like to assess progress. A line will be drawn at that point.
I hope this is helpful and answers your question. Let us know if you have further questions.
Andrew