hey im working ona project and need to assign a few of the tasks to work for day and night shifts for example between 2/2/11 and 5/2/11 i need day and night shift which equals up to six working days but at the moment project calculates it at 3 working days any way i can change 1 task at a time to have different working times and i have no resources allocated at this time so cant do it like that i hop my eplanition was good enough please get back to me asap as i am wasting time trawling the internet looking for answers

RE: working time

Hello Harry,

Hope you enjoyed your Microsoft Project Intro Intermediate course with Best STL.

Thank you for your question regarding working times.

Since it is not clear what you are trying to achieve I would like to see a sample copy of the file you are referring to.

Send it to me at: rl@stl-training.co.uk

I will take a look at your file and come back with a suitable answer.

Until then

Have a great day.
Regards,

Rodney
Microsoft Office Specialist Trainer

RE: working time

Thats oki rodney cant relly send this information over a little sensetive , but what i did was set my normal working day to 16 hours per shift to simulate 2 shifts thanks for youre speedy reply and i will be back with more questions in the future

harry .

MS Project tip:

Compare Work and Duration

Duration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field.