How do you compare a current project against its previous baseline?

RE: Microsoft Project

Hi Graham,

Thank you for your question and welcome to the forum.

Do you have multiple baselines in your project?

The original baseline is always called Baseline and to show the Baseline against the current plan go to the Gantt Chart Tools Format Tab, click Baseline and then select Baseline.

This will place grey bars along with your blue gantt bars.

I hope this answers your question.

Regards

Simon

Fri 19 Aug 2011: Automatically marked as resolved.


 

MS Project tip:

Avoid Accidental Constraints

The initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.)

View all MS Project hints and tips


Server loaded in 0.1 secs.