Forum home » Delegate support and help forum » Microsoft Project Training and help » Schedule Adjustments

Schedule Adjustments

resolvedResolved · High Priority · Version 2007

Cheren has attended:
Project Advanced course

Schedule Adjustments

I am entering %complete using the Update Task tool. I'm entering actual and remaining duration.
However the resultant date that is then calculated is wrong.

E.g task of 20 days that was due to start on 06/07 and finish on 02/08. It actually started on 08/07, and is as of the status date at 15/07 only 5% complete. I have entered actual start 08/07, 1 actual duration and 19 remaining. This should push the date out to 11/08 (19 days from status date 15/07, but MSP calculates this as 31/08.

It miscalculates on a number of tasks where progress is either ahead or behinf schedule or has not moved since the last status date. However on some other tasks, it calculates perfectly correctly!

Please help!

RE: Schedule Adjustments

Hi Cheren,

Thank you for your enquiry.

Is it possible to send a copy of the project with an exact description of what you are trying to achieve and the tasks that are causing problems.

Please send it to sk@stl-training.co.uk.

Regards

Simon

Tue 2 Aug 2011: Automatically marked as resolved.


 

MS Project tip:

Formatting Bar Text

To display notes or resource initials on the Gantt chart bars, choose Format, Bar Styles and the Text tab. Select the position you want to show the text i.e. Top or Inside etc, then choose the field name you are looking for from the drop down arrow. Type the first letter of the name to get quickly to the top of the letter range. Click OK.