Schedule Adjustments

ResolvedVersion 2007

Cheren has attended:
Project Advanced course

Schedule Adjustments

I am entering %complete using the Update Task tool. I'm entering actual and remaining duration.
However the resultant date that is then calculated is wrong.

E.g task of 20 days that was due to start on 06/07 and finish on 02/08. It actually started on 08/07, and is as of the status date at 15/07 only 5% complete. I have entered actual start 08/07, 1 actual duration and 19 remaining. This should push the date out to 11/08 (19 days from status date 15/07, but MSP calculates this as 31/08.

It miscalculates on a number of tasks where progress is either ahead or behinf schedule or has not moved since the last status date. However on some other tasks, it calculates perfectly correctly!

Please help!

RE: Schedule Adjustments

Hi Cheren,

Thank you for your enquiry.

Is it possible to send a copy of the project with an exact description of what you are trying to achieve and the tasks that are causing problems.

Please send it to sk@stl-training.co.uk.

Regards

Simon

Tue 2 Aug 2011: Automatically marked as resolved.

MS Project tip:

Autofit column width – Project (all versions)

At the top of the columns where each column name is located (Task Name, Duration, etc.), hover over the vertical column line which you want to move.

A short bold vertical line will appear, with horizontal arrows pointing left and right.

Left click and hold this icon and it will permit you to grab the column line, allowing you to move it left or right to your desired location.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.1 secs.