Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

microsoft project training courses - project

Forum home » Delegate support and help forum » Microsoft Project Training and help » microsoft project training courses - PROJECT

microsoft project training courses - PROJECT

ResolvedVersion Standard

Dorothy has attended:
Project Intro Intermediate course

PROJECT

This is just a wee question to get the project support started.......

Is there an easy way to remember the over poject summary button?

Thank you

RE: PROJECT

Hi Dorothy

Welcome to the forum and thank you for your question.

You can quickly turn on the project summary line by going to Tools > Options then from the view tab put a tick in the box Show Project Summary task. Is this the option you were looking for? If not do get back in touch.

Kind regards,

Andrew

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips