Progress line

How I can update progress bar?

RE: Progress line

Hi Agnieszka

Thank you for your question. There are a number of ways of progressing your tasks.

A quick way is to double click the name of the task and then on the general tab to key in the % complete you would like to record.

While this is quick a more accurate result can be achieved by clicking on the Task Ribbon, the clicking on the dropdown beside the "Mark on Track" button and choosing Update Tasks.

In the dialogue box that appears you can set useful values such as actual as well as entering real start and finish dates.

I hope this helps - do let me know if you have any further questions.

Kind regards,
Andrew

Tue 19 Jul 2011: Automatically marked as resolved.

MS Project tip:

Format individual bars on your GANTT chart

To draw attention to a bar on your Gantt chart simply double click it. From the dialogue box that opens make your selection of text and bar modifications.