progress line

Forum home » Delegate support and help forum » Microsoft Project Training and help » Progress line

Progress line

resolvedResolved · Low Priority · Version 2010

Agnieszka has attended:
Project Intro Intermediate course

Progress line

How I can update progress bar?

RE: Progress line

Hi Agnieszka

Thank you for your question. There are a number of ways of progressing your tasks.

A quick way is to double click the name of the task and then on the general tab to key in the % complete you would like to record.

While this is quick a more accurate result can be achieved by clicking on the Task Ribbon, the clicking on the dropdown beside the "Mark on Track" button and choosing Update Tasks.

In the dialogue box that appears you can set useful values such as actual as well as entering real start and finish dates.

I hope this helps - do let me know if you have any further questions.

Kind regards,
Andrew

Tue 19 Jul 2011: Automatically marked as resolved.


 

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips


Server loaded in 0.12 secs.