How do I show this?

RE: critical paths

Hello Lisa,

Hope you enjoyed your Microsoft Project 2010 Introduction course with Best STL.

Thank you for your question regarding how to show the critical path/tasks in Project.

Firstly, a little background... new tasks entered for a project will appear in the Gantt chart as blue in colour. In order to view the critical tasks which are on the critical path (start date to end date of your project) you must select the Format ribbon on the Gantt Chart Tools contextual tab. In this ribbon you will find a group called Bar Styles which contains a check box which can be selected for showing Critical Tasks.

Critical tasks will then appear in a red colour on the Gantt chart. Try it!

I hope this resolves your question. If it has, please mark this question as resolved.

If you require further assistance, please reply to this post. Or perhaps you have another Microsoft Office question?

Have a great day.
Regards,

Rodney
Microsoft Office Specialist Trainer

Thu 14 Jul 2011: Automatically marked as resolved.

MS Project tip:

Enter a Date

You can enter today's date (or tomorrow's date) in a date field, by simply typing in the word 'today'or 'tomorrow' and Project will insert the date for you.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.13 secs.