Kate has attended:
Project Advanced course

Project integration with Sharepoint

Further to an Advanced Project course in March with Garry, my colleague Paul and I would like to understand how you can import a Project into Sharepoint, as so far we have been unable to see how this is done.

RE: Project integration with Sharepoint

Hi Kate

Thanks very much for your question - can I just check your set-up? What version of Project are you using (including Project server if it's available) and what version of Sharepoint too.

Thanks

Andrew

RE: Project integration with Sharepoint

Hi Andrew

We are using Project 2007 with Sharepoint 2007. We do not currently have Project Server.

Kate

RE: Project integration with Sharepoint

Hi Kate

Thanks for coming back to me with the information.

We do provide consultancy and training services either onsite or over the phone and in this case we would probably need to assign one of our technical trainers to speak to you regarding your infrastructure.

One thing that might be helpful to know is that the version of Project 2007 and the infrastructure you are using will determine whether or not you can interact with Sharepoint.

Take a look at
http://office.microsoft.com/en-us/project/FX101757931033.aspx

We can arrange for one of our Project trainer/consultants to contact you to discuss best way of getting the applications to work together. Call us on the main number to discuss your requirements further.

Kind regards,
Andrew

RE: Project integration with Sharepoint

Hi guys,

I am trying to sync in multiple project plans ( on a MS Project 2010) with sharepoint 2010 on an existing list, but every time I try and sync in a project plan it automatically creates a new sharepoint list, because the previous one ( on which I initially intend to save the plan) is already in use.

I created a new sharepoint list and managed to sync it with a project plan. However I then created another project plan and tried to sync it with the same sharepoint list and this error occurs:

" The task list was synchronized to a different project plan. If you continue with the synchronization the task list will be appended with the project plan"

Any idea what to do ?

Thanks

RE: Project integration with Sharepoint

Navraj,

This is an old question that has already been marked as resolved. The trainers are not going to be alerted that a new question has been posted.

You should return to the forum home page and select 'ask a new question'.

Regards, Rich

MS Project tip:

Use Autofill in MS Project

a. Complete 1st entry
b. Select cell with entry to be copied
c. Click & drag autofill handle over the lines to also contain the same information. (the autofill handle is the little black square in the bottom right hand corner of the heavy lack outline on the selected cell)