Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

project resourcing

Forum home » Delegate support and help forum » Microsoft Project Training and help » Project Resourcing

Project Resourcing

ResolvedVersion 2007

David has attended:
Project Intermediate course

Project Resourcing

I am trying to develop a system that will allow me to report on the capacitiy of 4 staff members. Each member has 1 Project file. All are connected to one strategic overview file that shows their combined workload. I need to be able to the percentage of their time that each task takes, and therefore the percentage of their time that their workload as a whole takes (ie, are they overallocated).
How do I get them to input the % of their time that a task will take over its duration, without effecting the duration of the task?

RE: Project Resourcing

Hi David

Thanks for your question. It sounds like you have experienced tasks changing duration when resources are added or removed.

If a task doesn't necessarily go faster because more resources are working on it or slow down because someone leaves the task (meetings are a good example of this) then try splitting the screen (Window > Split) clicking on the task in question and removing the tick from Effort Driven, followed by OK. Now add or remove your resources and the Work will change, not the duration.

If you are adjusting assigned units and finding durations are changing incorrectly change the Task Type. It's just below the Effort Driven tick box on the split screen. Try setting it to fixed duration, clicking OK then adjusting the Unit percentages of your resources. Again you will find the duration remains unchanged but Work will be affected. It's useful to have the Work column added or perhaps Cost so you can keep an eye on the impact of changes you make.

Let me know if this helps or if you have any further questions.

Kind regards,
Andrew

Mon 30 Aug 2010: Automatically marked as resolved.

MS Project tip:

Autofit column width – Project (all versions)

At the top of the columns where each column name is located (Task Name, Duration, etc.), hover over the vertical column line which you want to move.

A short bold vertical line will appear, with horizontal arrows pointing left and right.

Left click and hold this icon and it will permit you to grab the column line, allowing you to move it left or right to your desired location.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.1 secs.