We are trying to get vertical grid lines on an Gnatt chart, showing for each day. Please advise how we do this as we can't get them to show.

RE: Gridlines

Hi Tracey

Thank you for your question. In the Gantt chart view go to Format > Gridlines then choose the Bottom Tier column from the list. The line type option is blank - choose a line type from the drop down and pick a colour then click OK.

I hope this helps. Let me know if you have any further questions.

Kind regards,
Andrew

MS Project tip:

Inserting Task Durations Quickly

When entering durations for your tasks simply use the single letters - m for min, h for hr, d for day, w for week, but mon for month. If default is set for days, you need only type the number, for example 3 for 3days, or 0.5 for half a day.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.1 secs.