Merging gantt charts

I have a number of separate gantt charts which I want to merge so that they cna be shown on one report. How can I do this?

RE: merging gantt charts

Hi Mark

Thank you for your question. One way to do this would be to create a new blank project then from the Insert menu choose Project... and browse to select the first plan you would like to incorporate. Move down to the next row in your project and insert the next plan. Repeat until they are all in your new temporary project file. You can open the plans up by clicking on the + symbol beside the title of each project.

The combined project is made up of live project data. So if you edit in the combined project and save your changes you will be given the opportunity to save the changes back to the respective sub projects as well.

I hope this helps - do let us know if you have any further questions.

Kind regards,
Andrew

RE: merging gantt charts

Hi Andrew

That's perfect.

Many thanks for your prompt repsonse.

Regards

Mark

MS Project tip:

Change default view – Project 2010

a. In Project, click on the File tab
b. Select General from left hand side (this should be the screen displayed by default)
c. Set the Default view dropdown box to your chosen option
d. Click OK to apply your changes

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.09 secs.