microsoft project course london - Milestone

ResolvedVersion Standard

dick has attended:
Project Introduction course

Milestone

create one

RE: milestone

set task duration to 0 days (zero days)

MS Project tip:

Inserting Task Durations Quickly

When entering durations for your tasks simply use the single letters - m for min, h for hr, d for day, w for week, but mon for month. If default is set for days, you need only type the number, for example 3 for 3days, or 0.5 for half a day.