How do i hide tasks in a schedule

If you have a long schedule but want to show only the key tasks how do you hide the other tasks.

Edited on Thu 29 Mar 2007, 15:33

RE: how do i hide tasks in a schedule

Double click on the task and then in general tab select hide task bar


 

MS Project tip:

Format individual bars on your GANTT chart

To draw attention to a bar on your Gantt chart simply double click it. From the dialogue box that opens make your selection of text and bar modifications.

View all MS Project hints and tips