microsoft.project.courses - Reporting and baselines

ResolvedVersion Standard

Kip has attended:
Project Intro Intermediate course

Reporting and baselines

Why do we need baselines, how do we use them ?

RE: Reporting and baselines

A baseline is the original project planused to track progress on a project. The baseline plan is a snapshot of your schedule at the time that you save the baseline and includes information about tasks, resources, and assignments. it also sets the original start date.

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.