Split tasks in Project
Is there a way of giving a penalty for splitting a task. E.g. There is time associated to setting up a task which recurs every time a task is re-started.
RE: Split tasks in Project
Hi James,
Thank you for your question.
There is no easy way of achieving this.
The only method I can think of is to manually enter the time in Resource Usage view.
I hope this helps.
Regards
Simon