Hi, I know this wasn't covered on my course, however, I hope you'll be able to help me. I'm having a problem with tasks automatically splitting and I don't understand why. I haven't resourced the plan so there shouldn't be any levelling taking place (although I did clear it just in case), but I can't get the tasks to unsplit.

Do you have any suggestions that I can try.

Many thanks
Angela

RE: Split Tasks

Hi Angela

Thank you for your question. Although there are no resources has any work or progress been added? You might also want to go to Tools > Resource leveling and choose Level Resources is it set to manual or automatic. Manual would be the preferred setting.

Let me know if you find anything.

Kind regards,
Andrew

RE: Split Tasks

Hi,

This question has now been left unattended for a while.

We like to keep down the large number of active forum posts we receive.

As we are waiting for your response for further information to help resolve your issue, we will be automatically marking this question as resolved in the next 5 days (unless you post a follow-up within that time).

We look forward to hearing from you.

Thank you.
Regards, Rich

Wed 25 Nov 2009: Automatically marked as resolved.

MS Project tip:

Use Autofill in MS Project

a. Complete 1st entry
b. Select cell with entry to be copied
c. Click & drag autofill handle over the lines to also contain the same information. (the autofill handle is the little black square in the bottom right hand corner of the heavy lack outline on the selected cell)