How do you produce a drop line program.
RE: Program Generation
Hi Andy
Thank you for your question. You can add drop lines to your project by going to Tools > Tracking > Progress lines
On the right of the dialog box you can enter the date or dates on which the progress (or drop) lines should appear.
I hope this helps - let mw know if you have any further questions.