How do you produce a drop line program.

RE: Program Generation

Hi Andy

Thank you for your question. You can add drop lines to your project by going to Tools > Tracking > Progress lines

On the right of the dialog box you can enter the date or dates on which the progress (or drop) lines should appear.

I hope this helps - let mw know if you have any further questions.

Kind regards,
Andrew

Mon 12 Oct 2009: Automatically marked as resolved.


 

MS Project tip:

Format individual bars on your GANTT chart

To draw attention to a bar on your Gantt chart simply double click it. From the dialogue box that opens make your selection of text and bar modifications.