Tasks starting on working days only

I have delevoped a generic programme for use on different projects. The commencement date will change depending upon when the project will start. When i change the start date on want to ensure that any task that falls at a weekend starts on the next working day i.e. the following Monday.

How can this be done.

RE: Tasks starting on working days only

Hi Jeff

Thank you for your question. Project does this automatically for you. If the Standard Calendar has weekends as non working days tasks will always be moved to the next available working day.

I hope this helps.

Kind regards,
Andrew

Wed 30 Sep 2009: Automatically marked as resolved.

MS Project tip:

Show or hide toolbar ScreenTips

On the Tools menu, go to Customize, and then select Toolbars.
Click the Options tab.
put a tick or remove the tick from the Show ScreenTips on toolbars check box.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.09 secs.