Jeff has attended:
PowerPoint Intermediate Advanced course
Task Lists Reports
How do i produce a report that shows me the tasks lists / task to start on a week by week basis. i.e:
week 1 - tasks 1,2,3,4,5,6 etc
week 2 - tasks 7,8,9
week 3 - tasks 10,11 & 12
etc
RE: Task Lists Reports
Hi Jeff
Thank you for your question. For individual resources you can do this by going to the View menu then choose Reports then select the Assignments group. In that list there will be a report called Todo which generates a list by resource
Alternatively you can export your task information to Excel (File > Save As then choose Excel workbook as your format). Follow the process to export Tasks and on the field mapping step click on Base on Table. From the list select the Entry table and finish the wizard. You can then open the exported Excel file and sort and group in Excel
Kind regards,