How do I create a milestone
RE: milestone
Sean
Thanks for the question
Enter a zero 0 day in the duration part of the task
Good luck
Rich
Forum home » Delegate support and help forum » Microsoft Project Training and help » project server training london - Milestone
Sean has attended:
No courses
How do I create a milestone
Sean
Thanks for the question
Enter a zero 0 day in the duration part of the task
Good luck
Rich
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question.
Our Microsoft Qualified trainers will then respond within 24 hours (working days).
Frequently Asked Questions
What does 'Resolved' mean?
Any suggestions, questions or comments? Please post in the Improve the forum thread.
Ever feel lost on a large project file? In Gantt view, Task ribbon, Editing, click on the Scroll to Task tool to centre the task bar on your screen.
Shortcut Ctrl+Shift+F5
Same as Go to Selected Task in MS Project 2003.
Call for assistance
We will call you back