Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

microsoft project

ResolvedVersion 2007

Microsoft Project

Is there a way that dates inputed in Microsoft Project can be synchronised with the Outlook calendar?

RE: Microsoft Project

Hi Ana

Thank you for your question.Unfortunately MS Project doesn't directly synchronise with Outlook without additional software. Microsoft product Project Server allows tasks to populate your Outlook. There are also third party applications that achieve similar results which can be found searching online.

Kind regards,
Andrew

Thu 6 Aug 2009: Automatically marked as resolved.

MS Project tip:

Set default task type - Project 2010

a. In Project, click on the File tab
b. Select Options from left hand side
c. Click on Schedule to set the scheduling options
d. Set the Default Task type box to your chosen option
i. Generally if you plan/estimate your projects using durations you should use fixed duration, and untick the box New tasks are effort driven, if you plan/estimate with person hours use fixed work, or for plans estimated with the proportion of resources time use fixed units, and untick the box New tasks are effort driven)
e. Click OK to apply your changes

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.1 secs.