Barry has attended:
Project Introduction course
Multiple tasks on same line
Further clarity on splitting single line tasks into multiple dates or groups for such things like quarterly cyclical maintenance visits
RE: Multiple tasks on same line
Hi Barry
Thank you for your question. MS Project has a recurring task feature that can help. Go to Insert > Recurring Task and use the selectors to decide the pattern for your recurring task. Project will then create constrained tasks that fall on the dates that meet the pattern you set.
Kind regards,
Andrew