I can't remember how to shunt the start date for the whole programme forward by 4 weeks.

RE: MS Project

Hi Neil,

Thank you for your question and welcome to the forum.

If you want to change the Start Date of the project or programme, go to the Project menu and then Project Information.

Click on the Start Date calendar control and choose the new Start Date.

I hope this answers your question.

Regards

Simon

Fri 17 Jul 2009: Automatically marked as resolved.

MS Project tip:

Avoid Accidental Constraints

The initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.)