Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

project overview project

Forum home » Delegate support and help forum » Microsoft Project Training and help » Project Overview - Project Summary Report

Project Overview - Project Summary Report

ResolvedVersion 2003

Sarah has attended:
Project Management - Framework & Processes course

Project Overview - Project Summary Report

Problem still unresolved. (see earlier posting today).

I have amended the Resource Sheet to show the unit price per day and it STILL does not give logical answers.

eg ccy 200 per day should give me ccy 400 total for 2 man days. the result I get does not add up.

There must be another constraint that is defined elsewhere. I am using someone else's project plan btw.

PLEASE HELP!

RE: Project Overview - Project Summary Report

Hi Sarah

Thanks for the update - just out of training and got your message. Take a look at the Resource Usage view. Is your resource red (ie overallocated?) or are their hours on certain days edited so that there are more or less than the default 8 per day?

Have fixed costs been added to tasks? (insert the Fixed Cost column)

One way to trouble shoot the plan might be to change the day rate down to

MS Project tip:

Enter a Date

You can enter today's date (or tomorrow's date) in a date field, by simply typing in the word 'today'or 'tomorrow' and Project will insert the date for you.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.1 secs.