RE: mile stone
Steven
Thanks for the question
Enter a zero 0 day in the duration part of the task
Good luck
Tracy
Forum home » Delegate support and help forum » Microsoft Project Training and help » microsoft project course london - Mile stone
Steven
Thanks for the question
Enter a zero 0 day in the duration part of the task
Good luck
Tracy
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question.
Our Microsoft Qualified trainers will then respond within 24 hours (working days).
Frequently Asked Questions
What does 'Resolved' mean?
Any suggestions, questions or comments? Please post in the Improve the forum thread.
When you need to communicate important information to your project staff use Microsoft Project 2003 to send them a note using outlook or an e-mail system.
1.In a task sheet, select the task or tasks which you want to send a project note.
2.On the File menu, point to Send To, and then select Mail Recipient (as Schedule Note).
3.Under Address message to, select the recipients of your note.
Call for assistance
We will call you back