microsoft project course london - Mile stone

resolvedResolved · Low Priority · Version Standard

Steven has attended:
Project Introduction course

Mile stone

how to create a milestone

RE: mile stone

Steven

Thanks for the question

Enter a zero 0 day in the duration part of the task

Good luck