ss sf ff

ResolvedVersion 2007

John has attended:
Project Intermediate course

SS, SF, FF

Where do you locate this option?

RE: SS, SF, FF

Hi John

Thank you for your question

I assume you are referring to different dependency types Start to Start, Start to Finish etc

Create your task dependency in the normal way and then double click on the arrow head of the link. This will open the task dependency properties dialog, and you can select the required type there

Regards

Stephen

Thu 16 Apr 2009: Automatically marked as resolved.

MS Project tip:

Compare Work and Duration

Duration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field.

View all MS Project hints and tips