microsoft+project+training - filter resources task fields

Forum home » Delegate support and help forum » Microsoft Project Training and help » microsoft+project+training - Filter resources by task fields

microsoft+project+training - Filter resources by task fields

resolvedResolved · Low Priority · Version Standard

Brendon has attended:
No courses

Filter resources by task fields

I have a resource labelled "labour" which is used throught a project. I want my resource graph to show the "labour" usage for only selected tasks (which have been flagged). How can I filter a resource (labour) by a task field (flag1)?

RE: Filter resources by task fields

ON THE TOOLBAR THERE IS A FILTER BUTTON NEXT TO (ALL TASKS) SELECT THIS BUTTON WHICH LOOKS LIKE A FUNNEL AND THEN YOU WILL SEE A DROP-DOWN LIST ON EACH HEADING SUCH AS (START,FINISHING HEADING) SELECT THE DROP-DOWN LIST AND SELECT THE OPTION YOU REQUIRE


 

MS Project tip:

Giving Someone a Gantt Chart Snapshot

To pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010)

View all MS Project hints and tips


Server loaded in 0.06 secs.