microsoft+project+training - Filter resources by task fields

ResolvedVersion Standard

Brendon has attended:
No courses

Filter resources by task fields

I have a resource labelled "labour" which is used throught a project. I want my resource graph to show the "labour" usage for only selected tasks (which have been flagged). How can I filter a resource (labour) by a task field (flag1)?

RE: Filter resources by task fields

ON THE TOOLBAR THERE IS A FILTER BUTTON NEXT TO (ALL TASKS) SELECT THIS BUTTON WHICH LOOKS LIKE A FUNNEL AND THEN YOU WILL SEE A DROP-DOWN LIST ON EACH HEADING SUCH AS (START,FINISHING HEADING) SELECT THE DROP-DOWN LIST AND SELECT THE OPTION YOU REQUIRE

MS Project tip:

Change default view – Project 2010

a. In Project, click on the File tab
b. Select General from left hand side (this should be the screen displayed by default)
c. Set the Default view dropdown box to your chosen option
d. Click OK to apply your changes

View all MS Project hints and tips