How do you change the Start date of your project?

RE: Dates

Hi Aldo

Thank you for your question. If you are part way through planning your project and you want to change the start date turn on the Analysis toolbar (View > Toolbars > Analysis) then click on the Adjust date button and enter your new date.

I hope this is helpful - do let us know if you have any further questions.

Kind regards,
Andrew

Tue 10 Mar 2009: Automatically marked as resolved.

MS Project tip:

Enter a Date

You can enter today's date (or tomorrow's date) in a date field, by simply typing in the word 'today'or 'tomorrow' and Project will insert the date for you.